In May 2022 Marlborough Highways was responsible for the traffic management of the inaugural Barking BikeFest at Abbey Green in the London Borough of Barking and Dagenham. They were also tasked with installing and then removing a temporary racetrack on the roads surrounding the green, creating a 1.2km circuit. With thousands of attendees and hundreds of competitors, it was vital that the event took place in a safe, enjoyable, and orderly fashion, with disruption to the local community needing to be kept to a minimum.


The Tour Series is a fun, fast and free cycling event that takes place in town and city centres across the UK. The series sees Britain’s best male and female riders compete against each other in a unique team-based format, with Laura Kenny, Dani Rowe and Ed Clancy amongst the household names that have previously taken part. For the first time in three years the tour descended on the capital in May 2022, when the perimeter of Abbey Green in Barking was converted into a specially designed race circuit.
The Tour Series London leg formed part of the Barking BikeFest, in which amateur cyclists of all ages and abilities, were able to take part in separate community races alongside the professional competition, with prizes and medals given away in every category. In addition, the festival comprised live music from a band stand, BMX and mountain bike displays, a kids area featuring live entertainment, and the ‘Electric Avenue’ zone, showcasing green technology including e-bikes and electric cars. The organisers required a trusted partner to assistant manage the event logistics, with the safety and well-being of festivalgoers the number one priority.
As the contractor responsible for the setting up the racecourse, managing road closures and marshalling the routes into the festival site, Marlborough conducted extensive pre-planning in partnership with the event organisers and Barking and Dagenham Council. The roads used for the race circuit were resurfaced ahead of the event, with the works carried out at weekends to reduce disruption to residents and local businesses. The community was given advanced warning of the road closures and a strict schedule of works was devised, ensuring that the event set up and dismantle was carried out quickly and efficiently.
Working with local stakeholders, Marlborough operatives in high-visibility uniforms were fully briefed ahead of the event, so that they could manage the flow of cars, bicycles, and pedestrians in an effective manner. Throughout the day, friendly staff were on hand to provide the public, competitors and onsite broadcast teams filming the event, with the information and assistance they needed, to ensure that everybody had a safe and enjoyable experience.
Client Barking and Dagenham Council
Date 21 May 2022
Duration One day event with 2 months planning
Value: £25,000 excluding resurfacing works
Project
Team
Client savings
Quote from client
“I would like to thank you and your team for your efforts, the crews were professional, courteous, and hard working all day and ensured the event went without a hitch. You and the team were a credit to the company, demonstrating commitment and support to the London Borough of Barking and Dagenham.”
Nick Davies, Specialist Services Manager, Barking and Dagenham Council